Steady Lift Handles the Transportation and Installation of Engine
Construction of the Gazipur RPCL 100MW HFO Fired Power Plant is a part of a major plan to supply reliable power to the localities in Bangladesh. The power plants were expected to play a prominent role in the socio-economic development in the nation while meeting the demand for electricity presented in the localities. The Gazipur RPCL 100MW HFO Fired Power Plant that commenced its operations at a capacity of 150MW was later upgraded to 225MW under the authority of Bangladesh Power Development Board.

Load-In and Transportation of a 300-ton Engine
Steady Lift received the Engine (1,425 CM x 430CM x 631CM) at the jetty of the Port weighing 387 CBM.
Steady Lift first received and handled the items at the port. The Engine was first loaded on to a barge and transported ashore. The Engine was then transported to the project site in Gazipur on 9-axle lines.
By remaining flexible in the approach, using local expertise, ensuring effective communication with Steady Lift’s Far East branch and by mobilising an experienced transport crew, Steady Lift was successfully handle the project.

Leave Comment